Above is Kopi Shore Base, on the banks of the Kikori River, PNG.
|
20 inch diameter pipe string being pulled through a horizontal bore hole under Utitu Creek. Start of Export pipeline at CPF pump station and pig launcher. Makas rigsite. All the exploration rig sites are isolated and helicopter supported. |
|
| |
|
Kopi Shore Base under construction in 1990 as marshalling yard for construction of the 260km Kutubu oil pipeline.
|
Above - Crusher's pioneer survey crew near Lake Kutubu PNG in 1989. Last weld on the Kutubu Oil Pipeline joining 171km onshore and 90km offshore pipelines. Laying containment boom for Oil Spill Response training at Kopi. |
|
|